A product can look good in a photo and still be wrong in size, finish, quantity, hardware, voltage, or packing. After shipment, even a small mistake can stop installation.
Inspection does not remove every risk. It gives the buyer clear evidence and a chance to correct visible problems before the goods travel.
QUICK ANSWER
What should a pre-shipment inspection check?
Check identity, quantity, dimensions, materials, finish, workmanship, operation, accessories, labels, packing, and the approved documents. Use product-specific tests where required.
01
Prepare the inspection file
Give the inspector the purchase order, approved BOQ, drawings, sample photos or codes, product specifications, quantity, packing rules, and previous correction records.
The inspector should know which points are critical. A wrong window size is different from a small hidden paint mark.
02
Check quantity and product identity
Match cartons, units, models, colors, and accessories against the order and packing list. Open selected packages instead of checking only the outside labels.
For a mixed villa order, confirm that every room and item code is present. Missing small parts often create larger installation delays.
- Product and model code
- Ordered and finished quantity
- Color and finish code
- Hardware and accessory count
- Spare parts and installation items
- Carton and room labels
03
Check the product itself
Inspection points change by category. Tiles need size, shade, flatness, edges, and batch checks. Cabinets need dimensions, panels, finish, hardware, holes, and assembly. Windows need size, glass, operation, seals, drainage, and locks.
For electrical or performance products, visual inspection is not enough. Use the required test method and qualified laboratory or specialist where the project needs it.

04
Record problems clearly
A useful report shows the item code, defect, quantity affected, photo, measurement, and location. It should separate critical, major, and minor findings according to the agreed inspection plan.
The supplier should answer with a correction plan. If goods are repaired or remade, arrange a focused reinspection before release.
05
Inspect packing and loading readiness
Good products can still arrive damaged. Check inner protection, cartons, pallets, crates, corner guards, moisture protection, labels, weight marks, and fragile warnings.
For container loading, check package condition, container condition, loading order, weight distribution, securing, and final seal number.

FAQ
Frequently asked questions
When should inspection happen?
The order should be sufficiently complete and packed goods should still be accessible. The exact timing depends on the product and inspection type.
Can I inspect only by video call?
A video call is useful for communication, but it may not replace an independent physical check with measurements and records.
Does a passed inspection guarantee everything?
No. Sampling has limits, and hidden or performance issues may need special testing. A clear plan reduces risk but cannot remove it completely.
Who should approve the report?
The buyer or authorized project representative should review findings, supplier corrections, and the final release decision.